I-5 bridge project has Washington lawmakers feeling left out

Posted

The project to replace the aging Interstate 5 bridge over the Columbia River is set to hit a milestone next month with endorsements from key stakeholder groups, though legislators on the Washington side aren’t sure their priorities are being addressed in the project’s current form.

During a meeting of the Joint Oregon-Washington Legislative Action Committee on June 17, lawmakers from both states heard from project staff on the current “locally preferred alternative” (LPA) for the bridge replacement.

Much of the information provided at the meeting was discussed in prior meetings of the committee and other groups formed to steer how the project will develop. Key components of the project include an auxiliary lane in both directions over the Columbia River, a light rail extension from Portland’s MAX system from the Portland Expo Center to Evergreen Boulevard in Vancouver that follows I-5, a partial interchange on Hayden Island and the use of variable rate tolling to help fund the multi-billion-dollar project.

The LPA roughly doubles the width of the bridge on the automotive traffic level in each direction with the addition of auxiliary lanes and “safety shoulders,” which currently aren’t present on the existing structure. The bridge will also be “seismically sound” to handle potential earthquakes.

Interstate Bridge Replacement Program (IBRP) Administrator Greg Johnson mentioned program staff are expecting a preliminary navigation clearance determination from the U.S. Coast Guard “any day now.” That determination would include a proposed bridge height, which IBRP assistant administrator Ray Mabey said has the potential to be higher than the 116-foot clearance found in the failed Columbia River Crossing project of last decade. 

“Nothing has substantially changed in how the river is being used,” Mabey said. 

Though the determination is still pending, he noted the potential to require a “moveable span,” which would entail a greater cost.

Johnson said the movable span under consideration would be the “largest lift span in the world” and could cost an additional $400 million.

Mabey added a higher bridge would include complications for truck traffic rates and pedestrians. It wouldn’t benefit the majority of users, but would help with boat traffic.

During the three-hour meeting, Clark County lawmakers voiced concerns that the current direction of the project did not take Washingtonians’ interests into as high of consideration.

Sen. Ann Rivers, R-La Center, said the reduction of commute times is a chief focus for Washington, though that priority has fallen farther down the list.

“It just seems like everything Washington has wanted, we’ve gotten nothing of it,” Rivers said.

Sen. Lynda Wilson, R-Vancouver, said Washington has a number of goals for the project. At the top of that list is addressing congestion and freight mobility. 

“It always has been,” Wilson said.



Wilson brought up the impacts of variable rate tolling on the 70,000 daily commuters who use the bridge to get from Washington into Oregon.

“This is going to be an expensive project and it will be our taxpayers who are paying for it,” Wilson said.

Johnson responded by saying congestion is “fundamental” to the program, but it isn’t addressed by simply including more highway space. 

“We know that congestion is not solely solved by (the) addition of lanes. It’s solved by using the space that you have in the most efficient and effective way,” Johnson said.

He noted there will be future conversations with those involved with freight.

Through the program’s past work, Johnson said a third bridge that included a high-speed rail and a tunnel were considered but determined to not meet the program’s purpose and need. One of Clark County’s Democratic lawmakers, Rep. Sharon Wylie of Vancouver, said through that process the current proposal made the most sense.

“If I could be convinced that a tunnel was feasible, if I could be convinced that bus rapid transit would be equally as good in the long term, I would be happy to have a less controversial, more acceptable solution,” Wylie said. “But I have heard from several people that the best bridge is the one that gets built.”

Moving forward, the IBRP will host a slew of meetings in July to ask different stakeholder groups like city councils, transportation authorities and ports to endorse the LPA. The current timeline has the program moving into the environmental review process in July.

Rivers asked for a possible delay in the timeline since many Washington lawmakers feel their concerns aren’t being addressed. 

“It feels premature for us to be taking a vote when there are so many unanswered questions,” Rivers said.